This provides the schedule of work for the Plank Road Interchange Improvement Project. This schedule will be updated as the project progresses.


Obtain background information
 

Winter 2002 through Spring 2003

Project future traffic demands
  • First round of public involvement*

Spring 2003

Develop alternatives
  • Second round of public involvement*

Summer through Winter 2003

Finalize the preferred alternate and prepare preliminary construction plans for submission to PennDOT and Federal Highway Administration (FHWA)

Fall 2005

Final round of public involvement*

Winter/Spring 2006

PennDOT and FHWA review and approval of preferred alternative and environmental documentation

Spring 2006

* Each round of public involvement includes a Community Advisory Committee meeting, a Public Officials' briefing and a general Public Meeting.