This provides the schedule of work for the Plank Road Interchange Improvement Project. This schedule will be updated as the project progresses.
Obtain background information
|
Winter 2002 through Spring 2003 |
Project future traffic demands
- First round of public involvement*
|
Spring 2003 |
Develop alternatives
- Second round of public involvement*
|
Summer through Winter 2003 |
| Finalize the preferred alternate and prepare preliminary construction plans for submission to PennDOT and Federal Highway Administration (FHWA) |
Fall 2005 |
| Final round of public involvement* |
Winter/Spring 2006 |
| PennDOT and FHWA review and approval of preferred alternative and environmental documentation |
Spring 2006 |
* Each round of public
involvement includes a Community Advisory Committee meeting, a Public
Officials' briefing and a general Public Meeting.